Identify high-risk close-up stages
Typical hold points include wall framing and services before plasterboard, waterproofing before tiling, fire and acoustic separation before lining, roof bracing and insulation before sheeting, drainage before backfill and structural repairs before finishes.
Takeover projects may need additional hold points around first-builder interfaces and investigation openings.
Define the release criteria
The scope should state who inspects, what documents are required, which tests must pass and who authorises closure. A vague instruction to photograph work is not enough. Specify required views, measurements and certificates.
Where the insurer or consultant has requested access, allow reasonable notice without leaving the building exposed indefinitely.
Record non-conformance and correction
If work fails inspection, issue a dated item referencing the exact location. Photograph the condition, corrective action and compliant reinspection. Do not release the hold point on a promise that a concealed item will be fixed later.
Keep the records in the issue register and replacement builder's quality plan.
Coordinate programme and responsibility
Hold points should be built into trade sequencing and subcontract orders. The cost of inspection and potential delay should be acknowledged in the contract. Emergency weather protection can proceed while preserving evidence where closure cannot wait.
The final close-up package should include plans, photographs, test results, certificates and inspector sign-off.
Hold points drawn from defects found in practice
- wall-base openings remain accessible until anchor location, spacing, engagement and any torque testing are recorded
- roof cavities remain open until truss bracing, restraints, stiffeners and fixings are checked against the truss layout
- floor cavities remain open until joist fixing, blocking and restraint are verified
- fire and acoustic walls remain visible until service penetrations and wall-to-ceiling or roof-space junctions are inspected
- drainage remains exposed until levels, CCTV or pressure testing and bedding are complete
- waterproofing and threshold work remains visible until terminations, test results and photographic evidence are accepted
Practical takeaway: Hold points convert hidden work into verified work. They are one of the most effective controls available on a builder-recovery project.
How ARK Houses can help
ARK Houses builds hold points into the recovery scope and subcontract instructions. We collect the required measurements, tests, photographs and sign-off before releasing walls, ceilings, floors, roofs or drainage for close-up.
Discuss Your Builder Recovery ProjectThis article provides general construction information only. It is not legal, financial or insurance advice. HBCF cover, deadlines, insurer decisions, contract rights and project requirements depend on the policy, evidence and individual circumstances. Obtain appropriate professional advice for your matter.